PM217 : PROJECT MANAGEMENT

QUESTION 1 (Compulsory)

Total Marks: 30 Marks

Click here to access other questions

SUGGESTED SOLUTIONS
Solutions and allocated marks are indicated in green.
Return to
Question 1

(a)Consider the following statements:
(i)project management must be customer-focused ;
(ii)a good project manager should be skilled in the use of appropriate management tools ;
(iii)we must empower project managers if they are to operate effectively.
Expand briefly upon each statement,explaining exactly what the statement
means.[6 marks ]
(i)project management must be customer-focused :
project managers should pay more attention to the customer (1 mark);the worst failure is carrying out projects that fail to satisfy the customer (1 mark);
customers expect good products and services (1 mark);customer focus means repeat business (1 mark);customer satisfaction means easier completion (1 mark) any of these points,to a maximum of two marks
(ii)a good project manager should be skilled in the use of appropriate management tools :
managers should be skilled in cost/schedule control,business finance,risk management,negotiation,requirements definition one mark for each different skill identified,to a maximum of two marks
(iii)we must empower project managers if they are to operate effectively. they must be given the skills (1 mark);they must be given authority to make decisions without passing them up the chain of command (1 mark);they must be given profit and loss responsibilities (1 mark)
one mark for each point,up to a maximum of two marks
[6 marks ]

(b)The management of risk is an important part of project management.
(i)What are the main sources of risk on a typical project?[2 marks ]
(ii)How can historical data be used in risk management?[2 marks ]
(iii)What strategies can be adopted for coping with,or reducing the impact of,
identified risks?[2 marks ]
(i)The main sources of risk are technical risk (1 mark),market risk (1 mark), financial risk (1 mark),and human risk (1 mark)
one mark for each correct source,to a maximum of two marks[2 marks]
(ii)Historical data can be used to identify risks (1 mark)and to help assess risks (1 mark)in terms of likeli ood and impact.[2 marks ]
(iii)To cope with risks,once identified,we might:
•develop and enforce standards to help reduce the likelihood and reduce the impact
•insure against the risk
•establish contingency plans
one mark for each correct point,to a maximum of two marks [2 marks ]

(c)Requirements definition can involve the following four activities:
(i)learning about the customer organisation
(ii)identifying multiple customers and prioritizing needs
(iii)establishing a task force to assist in defining needs
(iv)educating the customer
In each case,describe briefly what the project personnel or analysts would be
expected to do,and explain why the activity is important.[12 marks ]
(i)in learning about the customer organisation ,personnel would be expected to find out about the context (1 mark)in which the product or system would be used,or examine the usage of any existing systems (1 mark).This is important ifwe are to obtain an understanding of what the customer really needs (1 mark).
(ii)in identifying multiple customers and prioritizing eeds ,personnel would be making a list of all interested parties (1 mark).The stakes that different parties have in the project should be identified and compared (1 mark).Market research might be required (1 mark).Important if we are to avoid conflicts between customers (1 mark),or to satisfy all the di fferent groups (1 mark).
(iii)in establishing a task force to assist in defining eeds ,personnel would put together a team representing the different sets of customers (1 mark),involving customers in needs analysis (1 mark).Important if we are to achieve sharing of ideas between different sets of customers (1 mark),or if we are to obtain a consensus (1 mark)regarding needs,or to achieve customer buy-in (1 mark).
(iv)in educating the customer ,the personnel would ensure that the customer understands their needs (1 mark),that the understand the rudiments of project management (1 mark),that they understand the ways in which needs can change (1 mark),that they understand the need for compromise (1 mark).This is important if customers are to have the right expectations (1 mark)and if they are to formulate their needs in a helpful fashion (1 mark). in each case,up to two marks for the explanation of activity ,and one mark for the explanation of why it is important;alternative explanations might be considered [12 marks ]

(d)Contracts for project work may be structured as fixed-price contracts or cost-plus contracts.
(i)Which form of contract is likely to involve higher administrative costs?Explain your answer.[3 marks ]
(ii)Which form of contract is more appropriate for a high-risk development project? Explain your answer.[3 marks ]
(i)A cost-plus contract is likely to involve higher administrative costs.(1 mark). This is because the buyer takes the risk (1 mark)and will want to monitor progress closely (1 mark).The contractor will need to spend more time and money reporting on their progress (1 mark). up to three marks for a good explanation;no explanation,no marks [3 marks ]
(ii)A cost-plus project is more appropriate for a high-risk development project,as a fixed price contract would be too risky for the supplier (1 mark).Estimates on costs are highly speculative (1 mark),so the contractor runs the risk of bankruptcy or default (1 mark).With a cost-plus contract,the contractor knows that their expenses are covered.(1 mark) up to three marks for a good explanation;no explanation,no
marks [3 marks ]