August
1999 QUESTION 2 Total Marks: 20 Marks |
Click here to access other
questions
Click to access |
(a) | What is System Development Methodology (SDM),
and what form might it take?
|
[4] |
(b) | What are the
advantages and disadvantages of purchasing a general SDM package over developing an
in-house SDM?
|
[4] |
(c) | What are the four primary questions
that the SDM should allow the project manager to answer?
|
[2] |
(d) | Explain, with the aid of an illustrative
example, why it is important that an SDM should break down the system development life
cycle into a series of stages. Your discussion, and the example, should make reference to
the five discrete stages that you have studied.
|
[10] |