August 1999
PM217 : PROJECT MANAGEMENT

QUESTION 2

Total Marks: 20 Marks

Click here to access other questions

Click to access
SUGGESTED SOLUTIONS
for Question 2

(a) What is System Development Methodology (SDM), and what form might it take?

 

[4]
(b) What are the advantages and disadvantages of purchasing a general SDM package over developing an in-house SDM?

 

[4]
(c) What are the four primary questions that the SDM should allow the project manager to answer?

 

[2]
(d) Explain, with the aid of an illustrative example, why it is important that an SDM should break down the system development life cycle into a series of stages. Your discussion, and the example, should make reference to the five discrete stages that you have studied.

 

[10]