April
1999 QUESTION 5 Total Marks: 20 Marks |
Click here to access other
questions
Click to access
|
(a) | One possible method of cost estimation and
work performance management is the fifty-fifty rule. With the support of a diagram,
describe in some detail how this rule works.
|
[4] |
(b) | A software development project initial
planning has been budgeted to complete at $1,000,000, over a development time frame of 15
weeks in 3 phases. The three phases as originally planned are as follows: Phase 1, lasting 5 weeks, with a planned cost of $600,000. Phase 2, lasting 7 weeks, with a planned cost of $300,000. Phase 3, lasting 3 weeks, with a planned cost of $100,000. However, due to complications in the actual development, the following took place: After 8 weeks of development, phase 1 has been completed at a cost of $640,000. However, phase 2, although started, has yet to be completed, and expenditure so far for the phase is at $240,000. Now using the fifty-fifty rule, together with your knowledge of the earned value approach, calculate the following:
|
|
(i) Schedule variance (SV), cost variance (CV), Cost performance index (CPI), and estimated cost at completion (EAC) for phase 1. | [4] | |
(ii) Schedule variance (SV), cost variance
(CV), Cost performance index (CPI), and estimated cost at completion (EAC) for phase 2.
|
[6] | |
(c) | Evaluation tests are frequently conducted in project management to see whether targets are met. Identify, and explain any three types of evaluation processes. | [6] |