April
1999 QUESTION 5 Total Marks: 20 Marks |
Click here to access other
questions
GRADE A
|
(a) | One possible method of cost estimation and work performance management is the fifty-fifty rule. With the support of a diagram, describe in some detail how this rule works. | [4] |
In a fifty-fifty rule,
the contractor assume to get half of its value when the project phase start. It will not get the other half until the project phase has to be completed, no matter it is a delay, on time or earlier. The total earn is only $250 due to the phase 3 haven't finish. |
||
(b) | A software development project initial
planning has been budgeted to complete at $1,000,000, over a development time frame of 15
weeks in 3 phases. The three phases as originally planned are as follows: Phase 1, lasting 5 weeks, with a planned cost of $600,000. Phase 2, lasting 7 weeks, with a planned cost of $300,000. Phase 3, lasting 3 weeks, with a planned cost of $100,000. However, due to complications in the actual development, the following took place: After 8 weeks of development, phase 1 has been completed at a cost of $640,000. However, phase 2, although started, has yet to be completed, and expenditure so far for the phase is at $240,000. Now using the fifty-fifty rule, together with your knowledge of the earned value approach, calculate the following:
|
|
(i) Schedule variance (SV), cost variance (CV), Cost performance index (CPI), and estimated cost at completion (EAC) for phase 1. | [4] | |
(ii) Schedule variance (SV), cost variance
(CV), Cost performance index (CPI), and estimated cost at completion (EAC) for phase 2.
|
[6] | |
(i) SV = BCWP - BCWS = 600,000 - 640,000 = - 40,000 CV = BCWP - ACWP CPI = BCWP/ACWP EAC = BAC / CPI (ii) CV = BCWP - ACWP CPI = BCWP / ACWP EAC = 1000 000 / 0.8523
|
||
(c) | Evaluation tests are frequently conducted in project management to see whether targets are met. Identify, and explain any three types of evaluation processes. | [6] |
Audits Financial audit is done by outside auditors, whose job is to review project account and check project cash flow. Quality
Assurance Bid/ No Bid Evaluation
|