1999 QUESTION 4 Total Marks: 20 Marks |
Click here to access other
questions
Click to access
|
The information given below relates to a construction project for which your company is about to sign a contract. Seven activities are necessary and the normal duration, normal cost, crash duration and crash cost have been derived from the best available sources. Each activity may be reduced to the crash duration in weekly stages at a pro-rated cost. This project incurs a fixed cost of $500 per week. | ||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||
(a) | Draw the network diagram for the above project
using the normal times for the activities involved.
|
[5] | ||||||||||||||||||||||||||||||||||||||||||||||||
(b) | What are the critical path activities for the
project? What is the expected project completion duration and cost?
|
[4] | ||||||||||||||||||||||||||||||||||||||||||||||||
(c) | Assume that the company wishes to complete the project in 26 weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
(i) Write down the time each path would take without crashing. | [3] | |||||||||||||||||||||||||||||||||||||||||||||||||
(ii) Copy and complete the following table: | [3] | |||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||
(iii) Use the table to justify what crashing
decisions you would recommend in order to meet the completion duration at the least
possible cost. Show your working clearly. |
[5] |