April
1999 QUESTION 4 Total Marks: 20 Marks |
Click here to access other
questions
GRADE A
|
The information given below relates to a construction project for which your company is about to sign a contract. Seven activities are necessary and the normal duration, normal cost, crash duration and crash cost have been derived from the best available sources. Each activity may be reduced to the crash duration in weekly stages at a pro-rated cost. This project incurs a fixed cost of $500 per week. | ||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||
(a) | Draw the network diagram for the above project using the normal times for the activities involved. | [5] | ||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||
(b) | What are the critical path activities for the project? What is the expected project completion duration and cost? | [4] | ||||||||||||||||||||||||||||||||||||||||||||||||
Critical path is A ® D ® F Expected project completion is 30 weeks Total cost = $21, 400 + 30 ( 500) = $ 36, 400
|
||||||||||||||||||||||||||||||||||||||||||||||||||
(c) | Assume that the company wishes to complete the project in 26 weeks. | |||||||||||||||||||||||||||||||||||||||||||||||||
(i) Write down the time each path would take without crashing. | [3] | |||||||||||||||||||||||||||||||||||||||||||||||||
A ® E 29 weeks A ® D ® F 30 weeks * critical B ® F 28 weeks C ® G 17 weeks
|
||||||||||||||||||||||||||||||||||||||||||||||||||
(ii) Copy and complete the following table: | [3] | |||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||
(iii) Use the table to justify what crashing
decisions you would recommend in order to meet the completion duration at the least
possible cost. Show your working clearly. |
[5] | |||||||||||||||||||||||||||||||||||||||||||||||||
Step 1 : A ® E 29 weeks A ® D ® F 30 weeks * critical B ® F 28 weeks C ® G 17 weeks Looking
at the critical path, it is cheapest to crash D by 1 week. Step 2: Looking at the critical path, it is
only possible to crash a Step 3: (option 1 ) therefore, it is better to crash A and B. Final chart: Total cost of new project = $35,
590
|