3. Projects and project management have been subjected to unprecedented levels of change, and increasing levels of complexity over the last two decades.

 

(a) List and describe five sources of change in project management.

 

[10]
(b) There are four key steps to implementing methods and procedures for managing complexity. List and explain the importance of each of these four steps.

 

[8]
(c) How can the phenomenon of ‘simplicity through increased complexity’ occur? [2]