1998 QUESTION 3 Total Marks: 20 Marks |
Click here to access other
questions
Click to access |
3. | Projects and project management
have been subjected to unprecedented levels of change, and increasing levels of complexity
over the last two decades.
|
|
(a) List and describe five sources of
change in project management.
|
[10] | |
(b) There are four key steps to implementing
methods and procedures for managing complexity. List and explain the importance of each of
these four steps.
|
[8] | |
(c) How can the phenomenon of simplicity through increased complexity occur? | [2] |