1999 QUESTION 1 (Compulsory) Total Marks: 30 Marks |
Click here to access other
questions
Click to access |
(a) |
Define what is meant by the term Software Project .
|
[2] |
(b) |
Describe the relationship to risk of each of the following aspects of project management. (i)Time horizon.[1 mark ] (ii)Rewards.[1 mark ]
|
[2] |
(c) |
Briefly describe three approaches used to build a sense of team identity on a project.
|
[3] |
(d) |
Identify and explain any four ways a system can be implemented.
|
[8] |
(e) |
(i)What is a structured walk-through?[2 marks ] (ii)Briefly describe any two rules for conducting a structured walk-through. [2 marks ]
|
[4] |
(f) |
Give one advantage and one disadvantage of the graphical approach used in Project Management?
|
[4] |
(g) |
Give three essential characteristics of a good system development method.
|
[3] |
(h) |
List four qualities that you would look for in hiring a good needs analyst. |
[4] |