PM217 : PROJECT MANAGEMENT

QUESTION 1 (Compulsory)

Total Marks: 30 Marks

Click here to access other questions

Click to access
SUGGESTED SOLUTIONS
for Question 1

(a)

Define what is meant by the term Software Project .

 

[2]
(b)

Describe the relationship to risk of each of the following aspects of project management.

(i)Time horizon.[1 mark ]

(ii)Rewards.[1 mark ]

 

[2]
(c)

Briefly describe three approaches used to build a sense of team identity on a project.

 

[3]
(d)

Identify and explain any four ways a system can be implemented.

 

[8]
(e)

(i)What is a structured walk-through?[2 marks ]

(ii)Briefly describe any two rules for conducting a structured walk-through. [2 marks ]

 

[4]
(f)

Give one advantage and one disadvantage of the graphical approach used in Project Management?

 

[4]
(g)

Give three essential characteristics of a good system development method.

 

[3]
(h)

List four qualities that you would look for in hiring a good needs analyst.

[4]