December
1999 QUESTION 3 Total Marks: 15 Marks |
Click here to access other
questions
Click to access |
(a) |
Give two limitations of an earned-value analysis of general trends in work performance.
|
[2] | ||||||||||||||||
(b) |
A software development company is handling a large project, which, because of its complexity,has been broken down into three stages.
(i)Calculate the Cost Variance and Schedule Variance for each stage.[3 marks ] (ii)Calculate the percentage of the job achieved for each stage.[2 marks ] (iii)Calculate the Cost Performance Index for each stage.[2 marks ] (iv)Calculate the Estimate at Completion factor for the project.[2 marks ] You must show your working for each calculation.
|
[9] | ||||||||||||||||
(c) |
Draw a Gantt chart and a cumulative cost curve for both of the following scenarios. (i)On time,within budget.[2 marks ] (ii)Cost and schedule overruns.[2 marks ] |
[4] |