December
1999 QUESTION 2 Total Marks: 15 Marks |
Click here to access other
questions
Click to access |
(a) |
Name any three approaches that may be applied to reduce the failure rate in a project.
|
[3] |
(b) |
Discuss any three problems associated with the traditional approach to project management.
|
[6] |
(c) |
Discuss any three benefits in choosing the new approach in project management. |
[6] |