August 1997
IM218: INFORMATION MANAGEMENT

QUESTION 3

Total Marks: 20 Marks

Click here to access other questions

Click to access
SUGGESTED SOLUTIONS
for Question 3

3. You have been made responsible for hardware acquisition within your organisation.
(a) The hardware acquisition process begins with a determination of needs. How can these needs be determined? [2]
(b) Once identified, hardware needs can be split into two separate categories: mandatory attributes and desirable attributes. Explain these two categories, and give at least two examples for each category. [6]
(c) What is a Request For Proposal? Is it a legal contract? [2]
(d) How might a Request For Proposal be formulated so that it can appears to be objective but actually guarantees the selection of a particular product? [2]
(e) Outline the form and content of a Request For Proposal, explaining the contents of each section. [8]