1998 QUESTION 1 (Compulsory) Total Marks: 20 Marks |
Click here to access other
questions
Click to access |
1. | (a) What are the duties of a typical project manager? | [4] |
(b) List and explain two different types of maintenance. | [4] | |
(c) Copy and complete the following diagram to
identify the different steps in the risk control cycle: Briefly explain each of the steps you that you have identified. |
[4] | |
(d) In auditing a computer system, we may
decide to audit around the computer, or to audit through the computer. Compare and
contrast these two approaches.
|
[4] | |
(e) In your own words, suggest at least two ways in which the turnover rate of staff may be related to the difficulty of recruiting qualified personnel. | [4] |