December
1999 QUESTION 3 Total Marks: 15 Marks |
Click here to access other
questions
SUGGESTED SOLUTIONS |
(a) |
Give two limitations of an earned-value analysis of general trends in work performance. •The ability of accurate and timely cost data:unfortunately,the majority of the organisations have not established systems to collect such data (1 mark). •Second limitations is educational:for the earned value approach to work properly,everyone in the organisation should have an understanding of its mechanics (1 mark).
|
[2] | ||||||||||||||||||||||||||||||||||||||||||||
(b) |
A software development company is handling a large project, which, because of its complexity,has been broken down into three stages.
(i)Calculate the Cost Variance and Schedule Variance for each stage.[3 marks ] (i)Cost variance and schedule variance:
Award 2marks for using the correct formulas (deduct 1 mark for each incorrect formula);award 1 mark for correct arithmetic (no mark for any substantial error). (ii)Calculate the percentage of the job achieved for each stage.[2 marks ] (ii)Percentage of job achieved:
Award 1 mark for using the correct formulas (no mark if either is wrong);award 1 mark for correct arithmetic (no mark for any substantial error).[2 marks ] (iii)Calculate the Cost Performance Index for each stage.[2 marks ] (iii)Cost performance index:
Award 1 mark for using the correct formulas (no mark if either is wrong);award 1 mark for correct arithmetic (no mark for any substantial error).[2 marks ] (iv)Calculate the Estimate at Completion factor for the project.[2 marks ] You must show your working for each calculation. (iv)Estimate at completion: EAC =budgeted
cost at completion /CPI Award 1 mark for using the correct formulas (no mark if either is wrong);award 1 mark for correct arithmetic (no mark for any substantial error).[2 marks ]
|
[9] | ||||||||||||||||||||||||||||||||||||||||||||
(c) |
Draw a Gantt chart and a cumulative cost curve for both of the following scenarios. (i)On time,within budget.[2 marks ] (i)Detailed diagrams can be found in the Study Guide on page 9-8.If students give a correct diagram with proper labelling,award 2 marks;if they omit the labelling, then award 1 mark. (ii)Cost and schedule overruns.[2 marks ] (ii)Detailed diagrams can be found in the Study Guide on page 9-8.If students give a correct diagram with proper labelling,award 2 marks;if they omit the labelling, then award 1 mark.[2 marks ] |
[4] |