December 1999
PM217 : PROJECT MANAGEMENT

QUESTION 3

Total Marks: 15 Marks

Click here to access other questions

SUGGESTED SOLUTIONS
Solutions and allocated marks are indicated in green.
Return to
Question 3

(a)

Give two limitations of an earned-value analysis of general trends in work performance.

•The ability of accurate and timely cost data:unfortunately,the majority of the organisations have not established systems to collect such data (1 mark).

•Second limitations is educational:for the earned value approach to work properly,everyone in the organisation should have an understanding of its mechanics (1 mark).

 

[2]
(b)

A software development company is handling a large project, which, because of its complexity,has been broken down into three stages.

Stage no. Planned cost Actual cost Earned cost
1 32,000 28,000 28,000
2 40,000 44,000 46,000
3 20,000 28,000 23,000

(i)Calculate the Cost Variance and Schedule Variance for each stage.[3 marks ]

(i)Cost variance and schedule variance:
  CV =EC -AC SV =EC -PC
Stage 1 28 ,000 -28 ,000 =0 28 ,000 -32 ,000 =-4 ,000
Stage 2 46 ,000 -44 ,000 =2 ,000 46 ,000 -40 ,000 =6 ,000
Stage 3 23 ,000 -28 ,000 =-5 ,000 23 ,000 -20 ,000 =3 ,000

Award 2marks for using the correct formulas (deduct 1 mark for each incorrect formula);award 1 mark for correct arithmetic (no mark for any substantial error).

(ii)Calculate the percentage of the job achieved for each stage.[2 marks ]

(ii)Percentage of job achieved:
  EC /PC *100%
Stage 1 28 ,000 /32 ,000 *100% =87 .5%
Stage 2 46 ,000 /40 ,000 *100% =115%
Stage 3 23 ,000 /20 ,000 *100% =115%

Award 1 mark for using the correct formulas (no mark if either is wrong);award 1 mark for correct arithmetic (no mark for any substantial error).[2 marks ]

(iii)Calculate the Cost Performance Index for each stage.[2 marks ]

(iii)Cost performance index:
  CPI =EC /AC
Stage 1 28 ,000 /28 ,000 =1
Stage 2 46 ,000 /44 ,000 =1 .05
Stage 3 23 ,000 /28 ,000 =0 .82

Award 1 mark for using the correct formulas (no mark if either is wrong);award 1 mark for correct arithmetic (no mark for any substantial error).[2 marks ]

(iv)Calculate the Estimate at Completion factor for the project.[2 marks ]

You must show your working for each calculation.

(iv)Estimate at completion:

EAC =budgeted cost at completion /CPI
=BAC /CPI
=92 ,000 /((1 +1 .05 +0 .82 )/3 )
=92 ,000 /(2 .87 /3 )
=92 ,000 /0 .96
=95 ,833 .33

Award 1 mark for using the correct formulas (no mark if either is wrong);award 1 mark for correct arithmetic (no mark for any substantial error).[2 marks ]

 

[9]
(c)

Draw a Gantt chart and a cumulative cost curve for both of the following scenarios.

(i)On time,within budget.[2 marks ]

(i)Detailed diagrams can be found in the Study Guide on page 9-8.If students give a correct diagram with proper labelling,award 2 marks;if they omit the labelling, then award 1 mark.

(ii)Cost and schedule overruns.[2 marks ]

(ii)Detailed diagrams can be found in the Study Guide on page 9-8.If students give a correct diagram with proper labelling,award 2 marks;if they omit the labelling, then award 1 mark.[2 marks ]

[4]